Project Management: Unanet tasks and training materials
Unanet is an enterprise resource planning (ERP) system that CivicActions leverages for time tracking, planning, forecasting, and accounting. As a project lead, you're responsible for the following Unanet tasks:
- People planning and assignments
- Adjusting projections for holidays or other OOO
- Reviewing and approving timesheets
- Reviewing and approving expenses
- Runnings reports
- Plans v Actuals
- Planned Utilization
Key Unanet tasks for a project lead
- People planning and assignments (aka Plan with Grid)
- People planning and assignments by Day (aka Plan with Grid by Day)
- Reviewing and approving timesheets
- Reviewing and approving expenses
- Running reports: Plans vs Actuals
- Running reports: Planned Utilization
Adjust projections for holidays or other OOO
In general, resource allocations can be expected using the following ratios:
- If a FT resource devoted to the project, then 80%
- If an AD resource devoted to the project, then 65%
- If a PT resource devoted to the project, then 40%
From that place, then deduct - monthly - for any of the following:
- Holidays
- OOO
- Any other events, such as summits
Pro tip: For finding OOO dates on the calendar, use the CivicActions shared calendar and try searching "name OOO". This will allow you to isolate the forthcoming dates for the given person.